FACILITY EXPANSION PROJECT

  Expanding Our REACH Homepage | Phase 1 | Phase 2 | Phase 3 | Phase 4 | Donate

expanding our REACH

 

 

Timeline and Project Goals

 

2003:  REACH Studio Art Center founded in November.
2010:  Search begins for a larger space in Lansing’s REO Town vicinity.
2013:  Summer – Buildings purchased with grant from the Capital Region Community Foundation.
2013:  Fall – Clay Studio opens in first renovated building.
2014:   Demolition and re-roofing.  Spaces made for Courtyard, Youth Gallery, and parking. Large buildings gutted for future redevelopment.
2015:  Spring – Youth Gallery, Courtyard, and wall repair completed (Phase 1).
2015:  Summer – Main Hub (main and teen studio classrooms, offices, and reception) construction begins (Phase 2a).
2015:  Fall – Main Hub (Phase 2a) completed.
2016:  Facade, Main Hub details, and parking lot (Phase 2b) are completed.
2017:  Fiber Arts Studio, Media Lab, and Performance Studio are completed (Phase 3).
2018: Final renovations to original building and clay studio are completed.

 

Total Project Budget (Estimated):                 $1,200,000
Current Phase & Budget:                                      $320,000
Phase 2 Funding Status:                                       $265,000
Construction Status: Phase 1 complete.  Phase 2 under construction.

 

donate button

Click to donate to “Phase 2” of our Expansion Project!

 

This video was created in 2013 as we began our capital campaign. While some info is dated, the video will give you a good idea of our process for facility expansion

 

 

 